Progress continues. Concrete block masonry work continued Saturday for half a day and resumed this morning. The block stem wall to the first floor slab elevation should be completed by Wednesday. All underground piping, conduit, plumbing, electrical and mechanical stub work will continue through the week. the slad will probably get poured earlier next week. There is a lot of underground work to complete before placing fill and pouring the floor slab.